HANFORD 200-AREA (USDOE)
WASHINGTON
EPA ID# WA1890090078
EPA Region 10
Benton County
Richland

4th Congressional District

Other Names: US DOE-Hanford Site-200-Area
Last Update: May, 2010

Show details for Site DescriptionSite Description
Show details for Threats and ContaminantsThreats and Contaminants

Hide details for Cleanup ProgressCleanup Progress

In May 1989, EPA, the Washington State Department of Ecology (Ecology), and DOE entered into an Interagency Agreement and Consent Order to provide a legal and procedural framework for cleanup and regulatory compliance at the DOE’s waste sites at Hanford. EPA, DOE, and Ecology jointly developed an action plan that addresses Superfund and Resource Conservation and Recovery Act (RCRA)-related issues at Hanford.

Since 1992, approximately 175,437 pounds of carbon tetrachloride have been extracted from the soil through soil vapor extraction. In a separate action, approximately 26,356 pounds of carbon tetrachloride have been removed from groundwater to date (1.2 billion gallons pumped). In addition, another groundwater pump and treat system has removed 545 pounds of uranium and approximately 0.38 pounds of technetium-99. Eight hundred soil waste sites have been organized into 27 operable units for characterization and remediation. Characterization of these operable units is ongoing and is scheduled to be complete by 2011. However, due to other priorities (focus on River Corridor cleanup in the 100 and 300 Area NPL sites) and technical challenges, the Tri-Party agencies are proposing changes to the Tri-Party Agreement schedules to extend this period to 2016.

The partial decontamination and safe demolition of a plutonium concentration facility and three buildings at the Plutonium Finishing Plant (PFP) were completed, as well as the demolition of 54 structures ancillary to two former processing facilities. The Record of Decision for remediation of one of the processing facilities was completed, and remedial design work has begun. At the Plutonium Finishing Plant, stabilization of product material has been completed and the inventory of stored product has been shipped to South Carolina (completed in 2009). Fourteen buildings and structures were demolished in the 200 Area in 2009, including three in the 200-north area that used to store fuel from the reactors for temporary cooling before processing in the large facilities in the main part of the 200 Area.

Approximately 1,750 feet of pipeline leading to waste disposal locations in the western portion of the 200 Area was recently removed along with 400,000 tons of contaminated soil and then disposed of at the Environmental Restoration and Disposal Facility (ERDF), a modern Superfund landfill that meets RCRA technical requirements for a hazardous waste landfill. Over 9,340,000 tons of waste, including building rubble, contaminated soil, and burial ground contents have been removed from cleanup activities across the Hanford site and disposed of at ERDF. ERDF is being expanded with two new "supercells" that are the equivalent of four original disposal cells. Approximately 80,000 tons of contaminated soil and building demolition debris has been removed from sites in the 200-north area and the outer zone of the 200 Area. Several sites in the 200-north area have been verified as meeting cleanup objectives. About 97,000 tons of soil has been excavated from the BC Control Area and disposed of in ERDF. The BC Control Area was contaminated when animal intrusion occurred at the nearby BC Cribs and Trenches back when the cribs were in operation. Work is underway on cleaning up sites on the periphery of the central plateau. A removal action for simple sites on the periphery of the 200 Area (200-MG-1 operable unit) just commenced. Sites outside the core zone will be cleanup up consistent with what would meet unrestricted surface exposure.

Over 50,438 drum-equivalents (covers drums and boxes) have been retrieved from burial grounds out of an estimated total of 75,000 drums equivalents. Approximately half those drums contained transuranic waste that is destined for disposal at the Waste Isolation Pilot Plant (WIPP) in New Mexico. So far 15,957 drums have been shipped to WIPP. The last of the single-shelled tanks have been interim-stabilized per a Consent Decree. A vitrification facility is being constructed to glassify or vitrify waste from the tank farms in the 200 Area. The high-level glass will be sent offsite to a geologic repository, while the low-activity waste will be stored and eventually disposed of in the 200 Area in an approved disposal facility currently being constructed. Seismic design issues have been resolved and construction of the vitrification facility have been resumed.



Hide details for Regional ContactsRegional Contacts

SITE MANAGER(S):Craig Cameron
E-MAIL ADDRESS:cameron.craig@epa.gov
PHONE NUMBER:509-376-8665
COMMUNITY INVOLVEMENT COORDINATOR:Emerald Laija
E-MAIL ADDRESSlaija.emerald@epa.gov
PHONE NUMBER:509-376-4919
Information pertaining to this site is housed at the following location(s):
Public Access Room (Administrative Record)
2440 Stevens Center Place, Room 1101
Richland, Washington 99354