Project Title: Water Infrastructure - Holiday Harbor Sanitary Sewer Trunkline Project
Grant Information
| XP - 00T19601-1 |
 |  |  |
| EPA R9 | R09 - Region 9 |
| Water | wtr |
| 66.202 | Water |
|
|
 |
| Buckskin Sanitary District |
| Special District |
| AZ | 07 |
 | 039063941 |
| |  |
|
| 07/15/2011 | $485,000 |
| 06/15/2010 | 04/30/2012 |
Project Title & Description
Water Infrastructure - Holiday Harbor Sanitary Sewer Trunkline Project
The proposed project includes construction of gravity sewer and force main. This project also includes the construction of 17 manholes for the gravity system, air release valves for the force mains, and service connection stub-outs for future service connections.This project will connect 281 equivalent dwelling units to this new sanitary sewer system; sewage will temporarily flow to the Buckskin/Sandpiper wastewater treatment plant.