Eastern Michaud Flats Contamination

The Eastern Michaud Flats Superfund Site covers approximately 2,530 acres northwest of Pocatello, Idaho. It includes two adjacent phosphate ore processing facilities. The former FMC Corporation operated a facility from the early 1940’s until December 2001. The J.R. Simplot Company Don Plant is still an active facility. EPA issued a Record of Decision (ROD) for the site in 1998. A Supplemental Remedial Investigation and Feasibility Study (RI/FS) was issued in 2010 for the FMC portion of the site, while groundwater remediation at the Simplot site is ongoing.

Site Update

The FMC Corporation will begin cleanup work at their former phosphorus processing facility under a Unilateral Administrative Order from EPA. EPA’s Order requires FMC to design, implement and pay for the actions specified in the September 2012 Interim Record of Decision Amendment under oversight by EPA and the Shoshone-Bannock Tribes. Requirements include:
  • Develop detailed technical plans and specifications for the cleanup actions
  • Construct caps over contaminated soil
  • Treat groundwater to prevent contamination from moving toward the Portneuf River
Technical Documents

Key Superfund Documents:

Other Superfund Documents:

Site Information
Site Progress Profile
Site Summary (NPL PAD)
RCRA Site Summary
Pond 16 Removal Action
Decision Documents
Technical Documents
Fact Sheets
Photo Gallery
Site Map
Information Repository Locations
Freedom of Information Act (FOIA) Requests

Contact Us:

Project Managers:

Simplot Area and Off-Plant Areas
Jannine Jennings (jennings.jannine@epa.gov)
206-553-2724 or 800-424-4372

FMC
Jonathan Williams (williams.jonathan@epa.gov)
206-553-1369, or 800-424-4372 ext 1369

Community Involvement Coordinator:

Kay Morrison (morrison.kay@epa.gov)
206-553-8321, 800-424-4372 ext 8321

Cleanup Timeline
2011
Simplot OU- GW Extraction System completion (August);GW extraction and monitoring (ongoing);Completion of lower gypstack lining (Summer);Start of upper west compartment gypstack lining (Summer)
FMC OU -GW Monitoring Report (Spring); RCRA Post Closure Plan Modification (Fall); UAO RCRA Ponds (ongoing); Proposed Plan and Public Meetings (Fall);
Offplant OU -Vegetation monitoring (Summer/Fall)

Hide details for 20102010
Simplot OU -GW extraction and monitoring (ongoing) Start of lower gypstack lining (Spring); RD/RA consent decree amended (December)"
FMC OU -SRI Addendum Report Final (Jan); SFS Work Plan Approved (March); SFS Addendum Report Final (March); SFS Study Report Final (July); Pond 16S UAO compliance determination (November)
Off Plant Area- characterization and risk assessment reports (anticipated)
Show details for 2009 2009
Show details for 2008 2008
Show details for 1990 - 20071990 - 2007
FMC Supplemental Remedial Investigation and Feasibility Study (RI/FS): Simplot Documents: Off-site Documents RCRA Cleanup Actions: Other Documents: Fact Sheets and Outreach


Fact Sheets Public Meetings Southeast Idaho Update Newsletter
Information Repository Locations
Hard copy documents and information are available at the following locations during regular business hours:

    American Falls Library
    308 Roosevelt Street
    American Falls, ID 83211
    (208) 226-2335

    Idaho State University Library
    Government Documents
    850 South 9th Avenue
    Pocatello, Idaho 83209
    (208) 282-3152


    Shoshone-Bannock Library
    Tribal Business Center
    Pima Drive and Bannock Avenue
    Fort Hall, Idaho 83203
    (208) 478-3882


    EPA Region 10 Superfund Records Center
    1200 Sixth Avenue, Suite 900, ECL-076 (7th Floor)
    Seattle, WA 98101
    (206) 553-4494